Societatea Națională Nuclearelectrica S.A. (SNN) informs shareholders and investors that on November 16, 2026, SN Nuclearelectrica SA and the European Investment Bank signed the Financing Agreement worth 400 million euros for the completion of the Cernavodă NPP Unit 1 Retrofit Project, following the approval by SNN shareholders of the contracting of the financial support granted by the EIB worth 800 million euros, by EGEA Decision no. 9/29.10.2026. At the same time, the EIB announced that it is granting a first tranche of financing worth EUR 400 million to the operator of the Nuclearelectrica power plant for the replacement of components and the modernization of the systems of Unit 1.
The Board of the European Investment Bank (EIB) approved on 15 July 2026 the granting of a loan of EUR 800 million for the Cernavodă NPP Unit 1 Refurbishment Project (the Project), which for Romania and the nuclear energy industry in general meant historic financing, representing 25% of the total value of the project of approximately EUR 3.1 billion (excluding financing costs).
The EIB financing is structured in two financing contracts, each with a value of EUR 400 million, the second contract to be signed in 2027, correlated with the development stages of the Cernavodă NPP Unit 1 Refurbishment Project.
“The financing strategy of the Unit 1 Refurbishment Project is based on a mix of SNN’s own capital and funds attracted in the form of a loan. The loan contracted today will be used in the construction phase of the Project, an essential stage in the completion of the project. The financing provided by the EIB reconfirms the confidence in a complex investment project and in the long-term efficiency of nuclear energy. This loan also represents a historic first in terms of size, being the largest financing of the European Investment Bank for a company in Romania,” said Daniel Adam, CFO of SN Nuclearelectrica SA.
“The refurbishment of Unit 1 in Cernavoda will contribute to ensuring a stable supply of electricity at affordable prices and with low carbon emissions for millions of consumers,” said EIB Vice President Ioannis Tsakiris. “This flagship investment demonstrates our long-term commitment to supporting Romania’s energy security, economic competitiveness and sustainable growth.”
According to the development strategy approved by the shareholders, the Unit 1 Refurbishment Project is structured in three phases, the first of which, identifying the activities that are included for the purpose of the refurbishment, has already been completed in 2022. The current phase includes the activities necessary to prepare for the refurbishment such as: rigorous planning of the activities, conclusion of contracts, procurement of equipment with a long manufacturing cycle, construction of the infrastructure, obtaining the necessary permits, including securing financing. The third phase (2027-2030) represents the shutdown of Unit 1 for the actual refurbishment.
“The Unit 1 Refurbishment Project is well on track for the final stage, both operationally and in terms of securing financing. We have already concluded the framework agreement for project management services, engineering services contracts and supply of the reactor components to be replaced, the engineering, procurement and construction (EPC) contract, the refurbishment basis and we have started, a year ago, the civil construction works on the infrastructure necessary for the implementation of the project.
We will maintain the pace for the completion of all activities in the second and third phases of the project, on time and within the estimated costs. At the same time, we are securing financing for the third and most complex stage: the execution of the refurbishment. We are working with international teams of specialists, capitalizing on our accumulated experience and financing this project through solid partnerships with reputable financial institutions, such as the European Investment Bank”, said Mihai Laurențiu Gioară, General Manager of SN Nuclearelectrica SA.
The Unit 1 Refurbishment Project is a strategic project fully managed by Nuclearelectrica, the result of which is the extension of the life of Unit 1 by another 30 years and the delivery of 5 million MWh annually to the National Energy System, to ensure Romania’s energy security and resilience.
EIB support
The loan to the plant operator, Nuclearelectrica, represents half of the EIB’s planned €800 million financing for the 30-year life extension project for Unit 1.
The €3.1 billion project aims to ensure a reliable supply of low-carbon electricity and strengthen energy security.
The European Investment Bank (EIB) is releasing half of the planned €800 million financing for the retrofitting and life extension of a reactor at the Cernavoda nuclear power plant in Romania. The EIB is providing a first tranche of EUR 400 million to the plant operator, Nuclearelectrica, for the replacement of components and the modernisation of Unit 1 systems.
The Cernavoda nuclear power plant, located in south-eastern Romania, near the Black Sea coast, has two units that together provide around 20% of the country’s electricity production. Extending the life of Unit 1 will help maintain domestic energy production, strengthen energy security and support Romania’s transition to a lower-carbon energy system.
The project aims to extend the operational life of Unit 1 by 30 years, subject to compliance with regulatory requirements. The refurbishment works are scheduled to start in 2027 and last three years.
“The retrofit of Unit 1 in Cernavoda will help ensure a stable supply of affordable, low-carbon electricity for millions of consumers,” said EIB Vice-President Ioannis Tsakiris. “This flagship investment demonstrates our long-term commitment to supporting Romania’s energy security, economic competitiveness and sustainable growth.”
The total value of the investment amounts to EUR 3.1 billion. Other sources of financing are currently being negotiated with various export credit agencies, commercial banks, international financial institutions and Nuclearelectrica itself.
“The retrofit of Unit 1 represents a strategic investment in Romania’s energy security, ensuring a reliable supply of low-carbon electricity for decades to come,” said Mihai Gioară, CEO of Nuclearelectrica. “The EIB financing represents an important contribution to the realisation of this major project and to the extension of the operational life of the unit by another 30 years.”
The EIB loan, with a maturity of up to 22 years, contributes to the achievement of the European Union’s objectives of strengthening energy security, combating climate change and developing strategic infrastructure. The EIB’s Board of Directors approved in July 2026 the allocation of EUR 800 million in financing for Unit 1 of the Cernavoda nuclear power plant.