    27 November 2026
    Electricity
    energynomics

    The 48 MW/ 100 MWh project in Sânpaul, Mureș County, is set to enter commercial operation in Q3 2027. Regarding the sale of the Dumbrava project in Neamț County-the first in MetaWealth’s battery storage program in Romania-12 potential buyers have expressed interest.

    On November 25, MetaWealth, a European platform for real-asset investments, signed a 10 million euro contract with StarCharge. StarCharge will supply batteries with a total capacity of 100 MWh for the Sânpaul project-the second initiative within MetaWealth’s battery energy storage system (BESS) program in Romania-according to Agenda Construcțiilor. Located in Mureș County, the project has a total cost of 20 million euro. MetaWealth has received financing offers for Sânpaul, and financial close is on track for Q1 2027.

    StarCharge manufactures energy storage systems and electric vehicle charging equipment, with an annual turnover exceeding 600 million euro. All equipment for the Sânpaul site is scheduled to arrive in Q2 2027, with commercial operation slated for Q3 2027. On November 4, MetaWealth signed the acquisition agreement for a third project, located in Dolj County. With the projects in Dumbrava, Sânpaul, and Dolj, the portfolio reaches 300 MWh; all three are scheduled to enter commercial operation in 2027.

    “We have worked closely with institutional buyers and operators to understand their expectations for a storage asset, and all these insights have been incorporated into the Sânpaul project,” stated Richard McLaughlin-Duane, Chief Investment Officer at MetaWealth. “We are pleased to be working with StarCharge, a manufacturer included on BloombergNEF’s Tier 1 list, for optimized technical solutions. The company’s latest 6.25 MWh containers offer superior performance, lower operating costs, and maximum flexibility. Furthermore, the Sânpaul project has been designed to allow for expansion to four hours of storage capacity, which would bring the project to approximately 200 MWh.”

    In 2027, Unit 1 of the Cernavodă nuclear power plant-which accounts for approximately 10% of Romania’s electricity generation-is set to be taken offline for a 32-month refurbishment, according to Nuclearelectrica. As of November 1, the installed battery storage capacity in Romania stood at 1,262 MW / 2,713 MWh, based on data from Transelectrica.

    The sale process for the Dumbrava project-the first in the program-attracted 12 potential buyers. MetaWealth has received several offers from institutional investors, and the bidding period remains open until Q1 2027. According to MetaWealth, the offers received to date would generate a profit for MetaWealth investors. The sale is part of the program’s model: the first three projects are developed up to the point of commercial operation and then sold-to realize the development margin-while subsequent projects will remain in the MetaWealth portfolio.

    “Some of the major energy companies currently conducting due diligence have told us that our project in Dumbrava is one of the best in its category,” stated Michael Topolinski, founder and CEO of MetaWealth. “We intend to sell it, but we also have the option to retain the project and trade on the energy market once it enters commercial operation.”

    At the Dumbrava site in Neamț County, construction is underway; all equipment is already in Romania and is scheduled to arrive on-site in December, ahead of the project’s entry into commercial operation in Q2 2027. The project reached financial close in August with a 19 million euro funding package, consisting of a 7-year senior loan of approximately 10 million euro from CEC Bank, 5.5 million euro from the Topolinski family, and 3.5 million euro from investors in MetaWealth bonds-including 500,000 euro from BRD Asset Management.