Nuclearelectrica allocates 37.57 million lei for maintenance services of electrical systems and equipment at the Cernavodă Nuclear Electric Power Plant, in order to operate the plant under safe and nuclear security conditions, according to a notice of participation posted in the Public Procurement Electronic System (SEAP).

According to the cited source, the company that wins the tender will provide the materials and spare parts necessary to carry out these activities, within a contractual period of 24 months, effective delivery.

The contract will be awarded by open tender, on the basis of the best quality-price ratio. The deadline for receiving offers or requests to participate is November 15, 2023, 3:00 p.m.

Nuclearelectrica’s fields of activity are the production of electricity, heat and nuclear fuel.

Nuclearelectrica has two branches, without legal personality: CNE Cernavodă Branch, which operates Units 1 and 2 from CNE Cernavodă and auxiliary services, and FCN Pitesti Branch, the nuclear fuel factory. It is also the sole shareholder of the EnergoNuclear project company, holding 100% of the shares.