Individuals with “prosumer” status may apply-between 10:00 AM on November 20, 2026, and 11:59 PM on November 25, 2026-for the program focused on installing energy storage systems for electricity generated from renewable sources. Through this initiative, the Environmental Fund Administration (AFM) provides funding of up to 15,000 lei for the installation of batteries that allow for energy storage and subsequent use based on a household’s needs.
“The funding guidelines have been published in the Official Gazette, and we will open applications for individuals on November 20. Registration for installers began on November 16, and we already have 376 companies signed up. Through this program, we are supporting prosumers in storing energy that is not consumed immediately, allowing them to use it later and thereby reduce the amount of energy purchased from the grid. A key change for beneficiaries is the selection process, which is now based on a scoring system: the project’s specific characteristics matter, rather than the speed at which the application is submitted,” stated Natalia Intotero, Minister of Environment, Waters and Forests.
The funding provided by the AFM covers a maximum of 75% of the total project value, up to a limit of 15,000 lei (VAT included). The remaining balance must be covered by the beneficiary as a personal contribution. The maximum eligible cost standard is 1,500 lei per kWh of installed storage capacity, VAT included.
Project selection will be based on a total score of up to 100 points, awarded according to three criteria:
Storage system capacity, up to 40 points. The revised guide reduces the capacity required to obtain the maximum score from 20 kWh to 15 kWh. A 10 kWh system receives 20 points, with the score increasing proportionally up to 40 points for a capacity of 15 kWh.
Applicant’s own contribution, up to 35 points. An own contribution of 5,000 lei-given 15,000 lei in funding from the Environmental Fund Administration (AFM)-earns 10 points. The score increases progressively, reaching a maximum of 35 points for an own contribution of at least 15,000 lei.
Absence of prior non-reimbursable funding for storage systems, 25 points. This score is awarded to applicants who have not previously received such support from public funds.
The revised guide also allows the participation of prosumers who have previously received public funding for storage systems, provided that the new investment is distinct from the one previously implemented. Prior funding no longer constitutes grounds for ineligibility.
Furthermore, the guide clarifies how the total project value is determined by explicitly including expenses directly related to the implementation and commissioning of the investment. The funding guide, participation requirements, necessary documents, and program stages can be consulted on the Environmental Fund Administration’s website, in the section dedicated to the program.